It is reiterated that the EAC recommendation to rescind MOEF "Stop Work" Order dated 01-03-2011, be rejected outright and the Environmental .Clearance granted to Bhavanapadu 2640 MW TPP of ECEPL at Kakarapalli on 9-4-2009 be cancelled by MOEF, for the following reasons:
a) To begin with, MOEF relied on incorrect reports for granting Environmental Clearance (EC) dated 09-04-2009 to the project as
pointed out by NEAA
b) The ECEPL Project Site is in ecologically sensitive and important Wetlands, which is an excellent habitat for Migratory Birds and
is classified as IBAS, as pointed out by the Standing Committee of National Board for Wildlife. This fact was suppressed in the EIA
Report of the Project Proponent and by Srikakulam District Collector and the State Revenue Department while issuing G.O.Ms.No
No.1108 dated 05-09-2008, alienating government wet lands to an extent of Acs.3333.45 Cts. situated in Kakarapalli and other
villages for setting up ECEPL Power Project
'c) The detailed clarifications furnished by the Department of Environment and Forests , Govt of AP, vide letter No. 5447/ CZMA /2007
dated: 09.02.2009 , which were considered by EAC for recommending EC for the project, failed to point out the location of
the Project Site in ecologically sensitive Wetlands
d) MOEF Letter dated 01-03-2011 issuing directions under Section 5 of Environment (Protection) Act 1986 to ECEPL , also
acknowledges the fact that the project site is in Wetlands
e) The EAC recommendation in its 24 th Meeting held on 2-3 May 2011 that the Ministry may rescind "Stop Work" Order dated
01-03-2011, is based on the logic that "A zero base level assessment of the project is not a feasibility at this stage"
. This amounts to authorizing the illegal activity to continue by the project proponent , who managed to suppress the facts by using
the political clout, .
f) The MOEF land mark Order dated 14-01-2011 in the case of Adarsh Cooperative Housing Society directing that
"Unauthorized Structure built should be removed in its entirety and the area restored to its original condition " should be the guiding
factor for any decision to be taken by MOEF in the case of ECEPL Project and for upholding the "Rule of Environmental Law" and
Article 48-A of The Constitution of India